MINSKMETROSTROY UNITARY ENTERPRISE

The underground in Minsk is being constructed by MINSKMETROSTROY Public Unitary Construction Enterprise, a company with abundant experience and rich traditions (40 years in business in 2017), able to handle challenging tasks of a wide range of underground, architectural, decoration, specific, installation and other kinds of works. Underground building is a most difficult and laborious task in construction. Since established, our company has completed more than 37km of running tunnels with 29 stations: 15 stations in the 1st, Moskovskaya Line; 14 stations in the 2nd, Avtozavodskaya Line. Browse the website to find our portfolio, history and future perspectives.

ACTIVITIES:

  Building and reconstruction of underground railways, tunnels and other specific infrastructure;
  Production of building materials, assemblies and structures;
 Design, survey, engineering, pilot, trial works;
 Construction and renovation of general sites and objects;
 Trade and procurement;
 Consumer goods production.


Our company has a well developed manufacturing site in the industrial zone of Minsk where we can receive or dispatch almost any cargo by railroad. The site is common for a precast concrete factory, a mechanisation department, and a sleeper installation shop.
Every time building a new metro section we apply the most advanced solutions, equip stations and tunnels with relevant safety systems, CCTV, elevators for disabled persons, new modern finish materials.


PROJECTS COMPLETED AND IN PROGRESS:

assets/img/portfolio/work1.jpg

MINSK METRO
1ST LINE

(Moskovskaya, 15 stations)

MINSK METRO
2ND LINE

(Avtozavodskaua, 14 stations)

MINSK METRO
3RD LINE

(under construction)

NEWS:

October 30, 2018

Tunnel-mechanized complexes Alesya continues tunneling from station Vokzalnaya to station Kovalskaya sloboda after the forced stop.
As for the 30th October 183 rings have been assembled .


October 30, 2018

With the help of two non-mechanized shields ShN-1S MINSKMETROSTROY UE executes tunneling near Zhukovsky Street towards Aerodromnaya Street. As for the 30th October 390m of the left tunnel and 304 m of the right tunnel have been constructed