October 30, 2018

Tunnel-mechanized complexes Alesya continues tunneling from station Vokzalnaya to station Kovalskaya sloboda after the forced stop.
As for the 30th October 183 rings have been assembled .


26 June 2018

MINSKMETROSTROY listed at the National Board of Fame for the best performance in social and economic development among construction companies. Enacted by Decree of the President of the Republic of Belarus dated 26 June 2018 No. 255.

3 June 2018

A tourist jamboree for teams from Partyzanski District of Minsk takes place at Klevoe Mesto holiday camp (Vileyka Reservoir, Vileyka District, Minsk Region) on 1-3 June 2018. 3rd place for MINSKMETROSTROY.

10 May 2018

Today Alesya Alesya started the tunnel from Vakzalnaya station to Kavalskaya Slabada.
Tunnel-mechanized complexes disassembly and reassembly took a bit more than a month

19 April 2018

Alesya TBM disassembly underway at Yubileinaya station construction site. The heaviest component, 110 tons, detached and removed on 19 April 2018.

11 April 2018

MINSKMETROSTROY at the Partyzanski District Wall of Fame for the best performance in social and economic development in 2017 among construction companies.

30 March 2018

Main line tunnel between Vakzalnaya station and Yubileinaya station completed on 30 March 2018. Tunnel-mechanized complexes Alesya had gone 1597 metres and installed 1141 rings.

19 March 2018

19 March 2018 the second unpowered tunneler started the main line tunnel from marker 48 near Zhukovskogo Street to Aerodromnaya Street.
The leg is 398 metres long .

10 March 2018

On 10 March 2018 Alesya TBM passed by 1400-metre point at the main line tunnel between Vakzalnaya station and Yubileinaya Ploshcha. 1000 rings have been mounted.